New England Solar Farm & BESS

Projects

New England Solar Farm & BESS

PROJECT: New England Solar Farm & BESS

CLIENT: Transgrid

LOCATION: New South Wales

YEAR(S): 2021-2023

SCOPE: To design, manufacture and deliver 330kV Arteche instrument transformers

BACKGROUND: New England Solar is a 720MW solar and battery project built near Uralla in the NSW New England region. It is one of the largest solar projects to be participating in the National Electricity Market (NEM). 

As a long-standing supplier to Transgrid, GFF Power/Arteche were chosen to provide all the 330kV current transformers, capacitive voltage transformers, and power voltage transformers needed for the construction of the required 330kV substations.

As a long-standing supplier to Transgrid, GFF Power/Arteche were chosen to provide all the 330kV current transformers, capacitive voltage transformers, and power voltage transformers needed for the construction of the required 330kV substation. 

SERVICES PROVIDED

  • Design, manufacture and supply of Arteche current transformers, voltage transformers and power voltage transformers.
  • Ongoing project management, including provision of regular updates relating to anticipated delivery timeline.
  • Complete logistical assistance covering international freight, port clearance and delivery to site, including unloading.
  • Technical support as required by Transgrid throughout the project.

OUTCOMES

All equipment was manufactured to Transgrid’s specifications, produced in-line with the agreed schedule, and safely delivered to site per the project required timelines.